Building the World's
Largest and Most Strategic Uranium Mine

ROOK I SITE TOUR PRESENTATION

OCTOBER 2026

Picture 3

The Future

Of Good Energy

NexGen is positioned to produce up to 30 million pounds a year, enough uranium to power cities, states, and countries. 

NEXGEN | THE ASSET: ROOK I

One mine.

 

20% of the world’s uranium.

 

Over 50% of the western world’s supply.
 

2

Rook I Impact

239.6 million lb U₃O₈

Probable reserves at Arrow

2.37% U₃O₈ 

Average reserve grade

80.7 million lb U₃O₈

Inferred 

Up to 30 million lb / year

≈ one double decker bus by volume

ARROW RESERVE PROFILE

PRODUCTION POTENTIAL

≈ 20%

of current global primary uranium supply

of ore per day

3

PROJECT OVERVIEW

RESERVES AND PRODUCTION POTENTIAL

OPERATING SCALE

1,300 tonnes

≈ 20%

1.7% of global electricity

Picture 2

This is what 30 million pounds of uranium looks like in the real world.

Picture 22
Google Shape;369;p27
Google Shape;371;p27

Fueling enough carbon-free energy to power up to 46 million homes annually. Approximately 1 in 3 homes across the entire United States.

Removing the equivalent of 70 million cars from the road every single year.

Displacing more than 300 million tonnes of CO2 annually. Not offset. Displaced.

NEXGEN | THE INVESTMENT CASE: IMPACT

*Annual impact metrics (e.g., cars off the road, CO₂ displaced, homes powered) are calculated based on the Rook I Feasibility Study production schedule – approximately 30 million lbs U₃O₈ per year, Years 1–5, as outlined in the 2021 FS. These figures are illustrative only, do not imply any increase to reserves or extension of mine life, are subject to permitting, financing, operating performance, and market conditions, and do not include construction-phase impacts.

preencoded.png

4

Picture 2

Supply can’t keep up.

By 2040, primary uranium deficit is projected to reach 335 Mlbs per year¹

Uranium demand is surging and structurally inelastic.

A typical 15 - 20 year timeline from mine discovery to production, means supply cannot respond fast enough.

Higher prices - for longer - are essential to incentivize new production

Meeting forecasted 2040 demand of ~530 Mlbs will require mine supply to more than triple from today’s levels.

A Widening Uranium Supply Gap (Upper Scenario)¹

600

500

400

300

200

100

0

Gap of 16.5% (42 Mlbs)

2030

Gap of 28.7% (109 Mlbs)

2035

Gap of 63.0% (335 Mlbs)

2040

70%

60%

50%

40%

30%

20%

10%

0

Uranium requirements (Mlbs U₃O₈) - Demand

Expected primary supply (Mlbs U₃O₈) - Supply

1 World Nuclear Association (WNA), The Nuclear Fuel Report (September 2025 edition), Section 5.7 “Uranium supply and demand” — Figures 5.11–5.13 and Table 5.13 (Upper Scenario).

NEXGEN | THE MARKET: URANIUM’S MOMENT

Shortage in Million Pounds (Mlbs)

5

Picture 2

Why prices alone can’t fix a 20-year problem.

PRICE HAS NOT TRIGGERED A SUPPLY RESPONSE2

$17/lb U3O8

~2000 low

~5×

price increase

$90 /lb U3O8

today

140mlb mined

~2011

~14%

supply response at midpoint

~160mlb mined

Despite a 5× price increase,

global uranium supply grew just ~14% over 13 years.

The industry runs on 20-year timelines, by 2040, the world needs 335 million lbs per year. The gap cannot close without higher, sustained prices.

2. UxC, LLC – Uranium Market Outlook (UMO) (2025–2026)

NEXGEN | THE MARKET: SUPPLY TAKES TIME

today

6

URANIUM PRICE

Picture 2

<5

PROJECTS APPROVED

Why prices alone can’t fix a 20-year problem.

SUPPLY CONSTRAINED TODAY AND NEXT DECADE1

Mine development is a 20-year journey from discovery to production:

Last major mines came online in 2014 (Cigar) & 2016 (Husab):

since 2011

2040s

EARLIEST NEW DISCOVERED SUPPLY

comes online

Price signals sent today won’t deliver new supply until
the 2040s.

1 World Nuclear Association, The Nuclear Fuel Report (published September 2025, Reference Scenario) – for uranium requirements

NEXGEN | THE MARKET: SUPPLY TAKES TIME

7

Major construction has commenced.

PERMITTING TIMELINE

Sept 2023

Federal License Application Deemed Sufficient

Nov 2023

Provincial Environmental Assessment Approved

Nov 2024

Federal Technical Review Complete

FEED complete

Nov 19 2025

CNSC Hearing

(Part 1)

Feb 9–13 2026

CNSC Hearing

(Part 2)

Mar 5 2026

Final Federal Approval Granted

June 2026

Major Construction Began

CURRENT STATUS

Completed materially on time and schedule:

  • 3,000-ft airstrip complete
  • Advancing major earthworks and surface infrastructure
  • Site road networks

Current ongoing site construction — Q3 & Q4 2026:

  • Production and exhaust shaft mine terrace pads
  • Concrete foundations for the shaft headframes, hoist house and winch house
  • Installation of temporary freezing plant
  • Primary batch plant erected

NEXGEN | THE ASSET: ROOK I

preencoded.png
  • An additional 373-bed hard-walled camp,
    fully commissioned, complete and occupied
  • Effluent diffuser installation and road access​​

2019

Formal Commencement of EA and Licensing

Summer 2025

2025 Site Program

$100 m exploration program: airstrip, accommodation and dual traffic road access

8

Investing in People

6%

94%

ROOK I PROCUREMENT SPEND IN 2025

9

NEXGEN IMPACT

COMPETITIVE ADVANTAGE

Located 150 km north of La Loche and Clearwater River Dene Nation (combined population 4,500+), the Rook I Project is integrating local talent by creating training programs, hiring locally and developing skillsets that extend beyond mining¹.

94% of Rook I procurement spend in 2025 went to local suppliers and Indigenous partnered businesses  — totaling C$96.2 million.

700+

56%

Local Priority Area (LPA) students have participated in Company-funded skills, certification, and professional development programs since 2023.

Of NexGen's Rook I site employees in 2025 were from the LPA
in northern Saskatchewan.

EDUCATIONAL PARTNERS IN SASKATCHEWAN:

Other Suppliers

Local Priority Area Suppliers

Where We Are Today

10

ROOK I

CONSTRUCTION UPDATE

OCTOBER 2026

MAJOR CONSTRUCTION UNDERWAY

COMPLETE

3,000-foot airstrip

IN PROGRESS FOR THE REMAINDER OF 2026

Complete

SITE ACCESS

Active

SITE DEVELOPMENT

Additional 373-bed camp, bringing total capacity to 570 beds onsite and an additional 200 beds at a nearby camp

Diffuser installation

Earthworks, roads and construction pads

Shaft terraces, foundations and freeze facilities

Construction of waste management and construction facility pads

Temporary facilities and utilities

Airstrip expansion to 5,840 feet

Project Sequence

ROOK I

SCHEDULE OF MAJOR ACTIVITIES | CRITICAL PATH MANAGED

2025

Activity

Engeneering
and Design

2026

2028

2029

2027

2030

Procurement

Mobilization of Infrastructure

Exhaust Shaft

Production Shaft

Underground Development

Process Plant
& Effluent Treatment Plant

Pre-commissioning

Engeneering

Procurement

Mobilization of Site Ancillary Infrastructure

and Laboratory Facilities

Prepare and Sink Exhaust Shaft

Prepare and Sink Production Shaft

Underground Tailings Management

and Material Handling

Process Plant and Effluent Treatment Plant

Pre-commissioning

11

Phase 1

Site Development

BUILDING THE ESSENTIAL SURFACE INFRASTRUCTURE REQUIRED TO SUPPORT CONSTRUCTION AND OPERATIONS

ROOK I

SITE DEVELOPMENT

Phase 2

Shaft Construction

2028

2029

2027

Exhaust Shaft

Production Shaft

Freeze

15

Shaft Construction Schedule

ROOK I

SHAFT CONSTRUCTION

24 MONTHS TO HITTING BASEMENT

The ground setting validated by testing provides very high confidence

with respect to the schedule and cost of shaft sinking once in the basement setting

Q1

Q2

Q3

Q4

Q1

Q2

Q3

Q4

Q1

Q2

Q3

Q4

Pre-Sink

Surface Infrastructure

Shaft Sinking - Conventional Sink

Basement - Q2'28

Freeze

Surface Infrastructure

Pre-Sink

Shaft Sinking - Conventional Sink

Complete Q2'29

Basement - Q3'28

Complete Q4'29

HOW SHAFT CONSTRUCTION WORKS

ROOK I

GEOLOGICAL SETTING
AND GROUND FREEZING

HOW SHAFT CONSTRUCTION WORKS

ROOK I

SHAFT CONSTRUCTION

HOW SHAFT CONSTRUCTION WORKS

ROOK I

SHAFT CONSTRUCTION & UNDERGROUND DEVELOPMENT

Phase 3

Building the Mine

Picture 1

NEXGEN | THE CLOCK PROBLEM

Low material movement. High-value output.

High-grade ore enables just 3 trucks per day to feed the mill* - compared to hundreds or thousands at typical mining operations. And just 2 trucks leaving site - dramatically reducing infrastructure and environmental impact.

Low footprint. Low cost. Extraordinarily high value.

3

TRUCKS*

Ore is mined, brought to surface through the shaft and trucked to the mill

1,300

TONNES

Of ore processed through the mill

=

63

TONNES

Refined U3O8

157

BARRELS

Of U3O8 produced

Google Shape;435;p29
Google Shape;436;p29
Google Shape;437;p29

2

TRUCKS

Barrels shipped from site

Google Shape;444;p29
Google Shape;446;p29

DAILY INPUT

DAILY OUTPUT

NEXGEN | THE ASSET: ROOK I

*Based on maximum licensed capacity and 450 tonne trucks

Oil Barrel with solid fill
Oil Barrel with solid fill
Raw Materials with solid fill
Google Shape;446;p29

20

UNDERGROUND DEVELOPMENTS
​THROUGH CONVENTIONAL LONG HOLE STOPING

HOW SHAFT CONSTRUCTION WORKS

Operating the Mine

PROCESSING PLANT

ROOK I

OPERATING THE MINE

Best-in-Class Tailings Management

ROOK I

All tailings produced through the processing of ore will be stored underground as cemented paste, either in backfilled mine stopes or a purpose-built underground tailings management facility (UGTMF)

PROVEN TECHNOLOGY: NOVEL APPROACH

Underground uranium tailings storage has been conducted in other countries
(e.g., Olympic Dam)

Validated by geochemical and geotechnical testing programs ongoing since 2019

Storage of all tailings underground will be a first for a Canadian uranium project

Cemented tailings backfill extensively used in Canadian underground mines and in many parts of the world

24

Building the World's Largest, Lowest-Cost Uranium Mines

ROOK I

LOOKING AHEAD

THE VISION

FROM CONSTRUCTION TODAY TO COMMERCIAL PRODUCTION

25

Thank You

ROOK I · ​SASKATCHEWAN, CANADA

QUESTIONS & DISCUSSION

Picture 2
Picture 17

NEXGEN ENERGY LTD.

OCTOBER 2026

Travis McPherson | Chief Commercial Officer

tmcpherson@nxe-energy.ca

 

Monica Kras | VP, Corporate Development

mkras@nxe-energy.ca

 

Investor Relations

investors@nxe-energy.ca

Vancouver Office
Suite 3150, 1021 West Hastings Street

Vancouver BC V6E 0C3

The World Needs Good Energy.

 

We’re Building it.

Picture 3