BUILDING ONE
OF THE WORLD'S
LARGEST URANIUM MINES

CORPORATE PRESENTATION

SEPTEMBER 2026

OUR JOURNEY TO TODAY

2014

I. Discovery & studies

Arrow discovered

2017

2021

2023

2019

MAR 2026

Preliminary economic assessment

Feisibility study

II. Permitting

Environmental assessment

& licencing began

III. Construction

Provincial approval

Final federal approval

Major construction began

JUN 2026

2

MORE THAN A DECADE

OF PROJECT DEVELOPMENT

Technical studies, environmental assessment and licensing completed

WHY ROOK I MATTERS

239.6 million lb U₃O₈

Probable reserves at Arrow

2.37% U₃O₈ 

Average reserve grade

10.7 years

Initial mine life

Up to 30 million lb / year

≈ one double decker bus by volume

ARROW RESERVE PROFILE

PRODUCTION POTENTIAL

≈ 20%

of current global primary uranium supply

of ore per day

3

PROJECT OVERVIEW

RESERVES AND PRODUCTION POTENTIAL

OPERATING SCALE

1,300 tonnes

WHERE WE ARE TODAY

4

ROOK I

CONSTRUCTION UPDATE

SERPTEMBER 2026

MAJOR CONSTRUCTION UNDERWAY

COMPLETE

3,000-foot airstrip

IN PROGRESS FOR THE REMAINDER OF 2026

Complete

SITE ACCESS

Active

SITE DEVELOPMENT

Active

SITE ACCESS

Additional 373-bed camp, bringing total capacity to 570 beds

Diffuser installation

Earthworks, roads and construction pads

Shaft terraces, foundations and freeze facilities

Construction of waste management and construction facility pads

Temporary facilities and utilities

Airstrip expansion to 5,840 feet

PROJECT SEQUENCE

4

CRITICAL PATH MANAGED

ROOK I

SCHEDULE OF MAJOR ACTIVITIES

PHASE 1

SITE DEVELOPMENT

BUILDING THE ESSENTIAL SURFACE INFRASTRUCTURE REQUIRED TO SUPPORT CONSTRUCTION AND OPERATIONS

ROOK I

SITE DEVELOPMENT

PHASE 2

SHAFT CONSTRUCTION

SHAFT CONSTRUCTION SCHEDULE

4

ROOK I

SHAFT CONSTRUCTION

24 MONTHS TO HITTING BASEMENT

The ground setting validated by testing provides very high confidence

with respect to the schedule and cost of shaft sinking once in the basement setting

HOW SHAFT CONSTRUCTION WORKS

ROOK I

SHAFT CONSTRUCTION

PHASE 3

BUILDING THE MINE

PERMANENT INFRASTRUCTURE · MILL AND PROCESSING FACILITIES · UNDERGROUND DEVELOPMENT

ROOK I

BUILDING THE MINE

OPERATING THE MINE

HOW ORE MOVES FROM UNDERGROUND TO FINISHED PRODUCT

ROOK I

OPERATING THE MINE

SAFETY, AUTOMATION AND INNOVATION

ROOK I

OPERATING THE MINE

THE BUILD AHEAD

2026

2027

2029

2030

2028

Site construction, infrastructure and

shaft-site preparation

ROOK I

WHY INVESTORS SHOULD CARE

PLANNED CONSTRUCTION SEQUENCE

Ground freezing,

exhaust-shaft pre-sinking and process-plant construction

Complete the exhaust shaft, advance the production shaft and begin underground development

Complete the production shaft, install material-handling systems and connect the underground workings

Commission the processing facilities and begin commercial production

MOBILIZE & PREPARE

FREEZE & PRE-SINK

GO UNDERGROUND

CONNECT THE MINE

FIRST ORE

A CLEAR, SEQUENCED PATH TO FIRST PRODUCTION​

17

BUILDING ONE OF THE WORLD'S LARGEST, LOWEST-COST URANIUM MINES

ROOK I

LOOKING AHEAD

THE VISION

FROM CONSTRUCTION TODAY TO COMMERCIAL PRODUCTION

18

THANK YOU

ROOK I · ​SASKATCHEWAN, CANADA

QUESTIONS & DISCUSSION